Practice MCQ Questions and Answer on Time and Work

281.

A and B separately can build a wall in 12 and 16 days, respectively. If they work for each day alternatively, starting with A, in how many days will the wall be built?

  • (A) 723 days
  • (B) 1223 days
  • (C) 1323 days
  • (D) 634 days

282.

The labourers A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it 12 days, while A and B together can do it in 1313 days. The money will be divided in the ratio ?

  • (A) 4 : 5 : 6
  • (B) 4 : 7 : 5
  • (C) 5 : 7 : 4
  • (D) 5 : 6 : 8

283.

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • (A) 30
  • (B) 10
  • (C) 18
  • (D) 28

284.

A can complete work in 25 days and B can complete the same work in 20 days. They started the work together but B left after 4 days and A continued to work. In how many days will the entire work be completed?

  • (A) 25
  • (B) 20
  • (C) 28
  • (D) 22

285.

A completes 710 of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?

  • (A) 814days
  • (B) 1012days
  • (C) 1223days
  • (D) 1313days

286.

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

  • (A) 4 days
  • (B) 6 days
  • (C) 8 days
  • (D) 12 days

287.

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • (A) 4 days
  • (B) 5 days
  • (C) 6 days
  • (D) 7 days

288.

Twenty women together can complete a piece of work in 16 days, 16 men together can complete the same work in 15 days. The ratio of the working capacity of a man to that of a women is = ?

  • (A) 3 : 4
  • (B) 4 : 3
  • (C) 5 : 3
  • (D) 4 : 5

289.

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?

  • (A) 28 days
  • (B) 36 days
  • (C) 48 days
  • (D) 52 days

290.

A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternatively, with A beginning, then the work will be completed in ?

  • (A) 10 days
  • (B) 11 days
  • (C) 9 days
  • (D) 12 days