Practice MCQ Questions and Answer on Time and Work

51.

Naman does half the work as Gagan in 4/5 the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?

  • (A) 23 days
  • (B) 24 days
  • (C) 25 days
  • (D) 26 days

52.

A tyre has 3 punctures. The first puncture alone would have made the tyre flat in 9 minutes, the second alone would have done it in 18 minutes, the third alone would have done it in 6 minutes. If the air leaks out at a constant rate, then how long (in minutes) does it take for all the punctures together to make it flat?

  • (A) 2
  • (B) 6
  • (C) 4
  • (D) 3

53.

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

  • (A) 12 days
  • (B) 15 days
  • (C) 16 days
  • (D) 18 days

54.

A and B can do a job together in 7 days. A is 134  times as efficient as B. The same job can be done by A alone in :

  • (A) 913  days
  • (B) 11 days
  • (C) 1214  days
  • (D) 1613  days

55.

A can do piece of work in 15 days. B is 25% more efficient than A, and C is 40% more efficient than B, A and C work together for 3 days and then C leaves. A and B together will complete the remaining work in:

  • (A) 3 days
  • (B) 212 days
  • (C) 4 days
  • (D) 312 days

56.

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • (A) 712
  • (B) 10
  • (C) 12
  • (D) 14

57.

A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. They start the work together and completed the work such that B was not working on last 2 days and A did not work in last 3 days. In how many days (total) was the work completed?

  • (A) 727
  • (B) 797
  • (C) 657
  • (D) 827

58.

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

  • (A) 5
  • (B) 512
  • (C) 6
  • (D) 8

59.

The ratio of the efficiencies of A, B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:

  • (A) 96 days
  • (B) 99 days
  • (C) 102 days
  • (D) 93 days

60.

4 men and 10 women were put on a work. They completed 13 of the work in 4 days. After this 2 men and 2 women were increased. They completed 29 more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased ?

  • (A) 8
  • (B) 32
  • (C) 50
  • (D) 55