Practice MCQ Questions and Answer on Time and Work
51.
Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?
(A) 6:20 PM
(B) 6:30 PM
(C) 6:36 PM
(D) 6:42 PM
Solution:
According to question, Ganga begins at 9 am and she does 3 units/hours Saraswati begins at 10 am and she does 2 units/hours So by 11 am they complete 5 units Time (4 cycle of 2 hrs each + 4 units left) And now ganga will complete 3 unit out of 4 units in 1 hr Now, rest 1 unit work done by = hr Total time = 8 + 1 + = 9 hr Hence, Work finished at = 9 am + 9 hr = 6:30 PM Alternate Solution: Work done by Ganga in 1 hour = Work done by Saraswati in 1 hour = They are working alternatively with Ganga beginning the job. Work done in every two hours = + = Work done in 4 × 2 = 8 hours = = Remaining work = 1 - = In 9th hour, Ganga starts the work and does of the work Work remaining = - = In 10th hour, Saraswati starts the work Time needed to finish the remaining work 0.5 hours 30 minutes i.e., work will be completed in 9 hour 30 minutes, after 9 AM i.e., at 6:30 PM
52.
639 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?
(A) 210 days
(B) 213 days
(C) 214 days
(D) 215 days
Solution:
53.
42 women can do a piece of work in 18 days, How many women would be required do the same work in 21 days.
(A) 35
(B) 36
(C) 37
(D) 38
Solution:
Let X be the number of women required to finish the work in 21 days. Now, using Work Equivalence Method: 42 × 18 = X × 21 X = 36. Number of women required = 36
54.
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?
(A) 75
(B) 100
(C) 125
(D) 50
Solution:
Let 'n' number of men can required
55.
A takes twice as much time as B and thrice as much time as C to finalise a task. Working together, they can complete the task in 8 days. The time (in days) taken by A, B and C, respectively, to complete the task is:
(A) 42, 21, 14
(B) 60, 30, 20
(C) 54, 27, 18
(D) 48, 24, 16
Solution:
Efficiency of A : B : C = 1 : 2 : 3 Total work = 8 × (A + B + C) = 48 Time taken by A → = 48 days Time taken by B → = 24 days Time taken by C → = 16 days
56.
A and B can do a work in 12 days and 18 days, respectively. They worked for 4 days after which B was replaced by C and the remaining work was completed by A and C in the next 4 days. In how many days will C alone complete 50% of the same work?
(A) 24
(B) 18
(C) 21
(D) 36
Solution:
4 day work = 5 × 4 = 20 Remaining work = 36 - 20 = 16 (A + C) complete in 4 days A + C 3 + C = 4 C = 1 50% of work = = 18 C do = = 18 days
57.
Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?
(A) Rs. 600, Rs. 550, Rs. 250
(B) Rs. 600, Rs. 525, Rs. 275
(C) Rs. 600, Rs. 500, Rs. 300
(D) Rs. 500, Rs. 525, Rs. 375
Solution: ∴ Ratio of wages of the first man, second man and boy
58.
A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:
(A)
(B)
(C)
(D) 60
Solution:
Let x be the required number of days Given,12 men and 12 women can complete a work separately in 14 days and 21 days respectively Then, 12 men's 1 day work = And, 12 women's 1 day work = Then ,12 women's 3 days work = = The remaining work = = Man's group leaves 3 days before the completion of work That is, they were working together for x - 3 days Thus, we have work left to be done in last 3 days by the women's group. This also means th of work has been done by both the groups (before men left) Now, (12 men + 12 women)'s 1 day work = = i.e., work is done by 2 groups in 1 day. So, of work is done by 2 groups together in = days Total time take to complete the work will be = + 3 =
59.
A manufacturer builds a machine which will address 500 envelopes in 8 minutes. He wishes to build another machine so that when both are operating together they will address 500 envelopes in 2 minutes. The equation used to find how many minutes x it would require the second machine to address 500 envelopes alone, is = ?
(A)
(B)
(C)
(D)
Solution:
Number of envelopes addressed by first machine in 1 minute Number of envelopes addressed by second machine in 1 minute Number of envelopes addressed by both machine in 1 minute
60.
Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:
(A) 39 min.
(B) 46 min
(C) 40 min.
(D) 45 min.
Solution:
Pipe A can fill empty tank in 36 min. Pipe A can fill the tank = = 2.77% per minute Pipe B can fill empty tank in 45 min. Pipe B can fill the tank = = 2.22% per min. A and B can together fill the tank = (2.77 + 2.22) ≈ 5% per minute So, A and B can fill the tank in 7 min. = 7 × 5 = 35% of the tank Rest tank to be filled = 100 - 35 = 65% C can empty the full tank in 30 min. C can empty the tank = = 3.33% per min. C is doing negative work i.e. emptying the tank A, B and C can together fill the tank, = 2.77% + 2.22% - 3.33% = 1.67% tank per minute So, A, B and C will take time to fill 65% empty tank, = = 39 min. (Approx)