Practice MCQ Questions and Answer on Time and Work

61.

If m men can do a work in r days, then the number of days taken by (m + n) men to do it is :

  • (A) m+nmn
  • (B) m+nmr
  • (C) mrm+n
  • (D) r(m+n)mn

62.

A alone can do 25 of a work in 12 days. B is 25 percent more efficient than A. C alone can do the same work in 12 days less than B. D is 25 percent less efficient than C. If they all work together, then the work will be completed in how many days?

  • (A) 30047
  • (B) 24053
  • (C) 18043
  • (D) 20051

63.

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

  • (A)  445 days
  • (B)  313 days
  • (C)  514 days
  • (D) 223 days

64.

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

  • (A) 5
  • (B) 512
  • (C) 6
  • (D) 8

65.

60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?

  • (A) 10
  • (B) 15
  • (C) 18
  • (D) 20

66.

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • (A) 712
  • (B) 10
  • (C) 12
  • (D) 14

67.

A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take ?

  • (A) 15 days
  • (B) 12 days
  • (C) 16 days
  • (D) 14 days

68.

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

  • (A) 1313days
  • (B) 14 days
  • (C) 15 days
  • (D) 1623days

69.

A and B can do a job in 10 days and 5 days respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 40% of the job?

  • (A) 15 days
  • (B) 18 days
  • (C) 10 days
  • (D) 12 days

70.

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. In how many days C alone can do the same work ?

  • (A) 5 days
  • (B) 6 days
  • (C) 10 days
  • (D) 12 days