Practice MCQ Questions and Answer on Time and Work
61.
A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?
(A) 20 days
(B) 24 days
(C) 36 days
(D) 72 days
Solution:
(M + B)'s 1 day's work =$$\frac{1}{{24}}$$ (M + B)'s 20 day's work + M's 6 day's work = 1 $$\eqalign{ & \Rightarrow {\text{M's 6 day's work}} \cr & = \left( {1 - \frac{1}{{24}} \times 20} \right) \cr & = \frac{4}{{24}} = \frac{1}{6} \cr & \Rightarrow {\text{M's 1 day's work}} \cr & = \frac{1}{6} \times \frac{1}{6} \cr & = \frac{1}{{36}} \cr & \therefore {\text{B's 1 day's work}} \cr & = \frac{1}{{24}} - \frac{1}{{36}} \cr & = \frac{1}{{72}} \cr} $$ Hence, the boy alone can do the work in 72 days.
62.
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?
(A) 4
(B) 5
(C) 7
(D) 8
Solution:
$$\eqalign{ & {\text{C's 3 day's work}} \cr & = \left( {\frac{1}{{15}} \times 3} \right) \cr & = \frac{1}{5} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 2 day's work}} \cr & = \left[ {\left( {\frac{1}{{12}} + \frac{1}{{15}}} \right) \times 2} \right] \cr & = \left( {\frac{3}{{20}} \times 2} \right) \cr & = \frac{3}{{10}} \cr & \therefore {\text{Remaining work}} \cr & = \left[ {1 - \left( {\frac{1}{5} + \frac{3}{{10}}} \right)} \right] \cr & = \left( {1 - \frac{1}{2}} \right) \cr & = \frac{1}{2} \cr & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{10}} + \frac{1}{{12}} + \frac{1}{{15}}} \right) \cr & = \frac{{15}}{{60}} \cr & = \frac{1}{4} \cr} $$ $$\frac{1}{4}$$ work is done by A, B ans C in 1 day. ∴ $$\frac{1}{2}$$ work is done by A, B and C in $$\eqalign{ & = \left( {4 \times \frac{1}{2}} \right) \cr & = {\text{2 days}} \cr & {\text{Total number of days}} \cr & = \left( {3 + 2 + 2} \right) \cr & = 7 \cr} $$
63.
A can do in one day three times the work done by B in one day. They together finish $$\frac{2}{5}$$ of the work in 9 days. The number of days by which B can do the work alone is = ?
(A) 90 days
(B) 120 days
(C) 100 days
(D) 30 days
Solution:
Let time taken by A alone in doing work be x days ∴ Time taken by B alone = 3x days $$\eqalign{ & {\text{A's 1 day's work}} = \frac{1}{x} \cr & {\text{B's 1 days work}} = \frac{1}{{3x}} \cr & \because {\text{A and B together finish}} \cr & = \frac{2}{5}{\text{work in 9 days}}{\text{.}} \cr} $$ ∴ Time taken by A and B in doing whole work $$\eqalign{ & = \frac{{9 \times 5}}{2} \cr & = \frac{{45}}{2}{\text{ days}} \cr} $$ According to given information we get $$\eqalign{ & \therefore \frac{1}{x} + \frac{1}{{3x}} = \frac{2}{{45}} \cr & \Rightarrow \frac{{3 + 1}}{{3x}} = \frac{2}{{45}} \cr & \Rightarrow \frac{4}{{3x}} = \frac{2}{{45}} \cr & {\text{By cross - multiply we get }} \cr & \Rightarrow 2 \times 3x = 4 \times 45 \cr & \Rightarrow x = \frac{{4 \times 45}}{{2 \times 3}} \cr & \Rightarrow x = 30{\text{ days}} \cr & {\text{Time taken by A}} \cr & = x{\text{ days}} \cr & = {\text{30 days}} \cr & \therefore {\text{Time taken by B}} \cr & = 3x{\text{ days}} \cr & = 3 \times 30 \cr & = 90{\text{ days}} \cr} $$
64.
X can copy 80 pages in 20 hours, x and y together can copy 135 pages in 27 hours. Then y can copy 20 pages in ?
Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:
(A) $$\frac{2}{3}$$ hours
(B) $$\frac{3}{4}$$ hours
(C) $$\frac{3}{2}$$ hours
(D) $$\frac{4}{3}$$ hours
Solution:
Time taken by A =x hours. Therefore taken by A, B and C together = (x - 6) Time taken by B = (x - 5) Time taken by C = 2(x - 6) Now, rate of work of A + Rate of work of B + Rate of work of C = Rate of work of ABC. $$ \Rightarrow \frac{1}{x} + \frac{1}{{x - 5}} + \frac{1}{{2\left( {x - 6} \right)}} = \frac{1}{{x - 6}}$$ On solving above equation, we get x = 3, $$\frac{{40}}{6}$$ When x = 3, the expression (x - 6) becomes negative, thus it's not possible. $$ \Rightarrow x = \frac{{40}}{6}$$ Time taken by A & B together = $$\frac{1}{{\frac{3}{{20}} + \frac{3}{5}}}$$ = $$\frac{4}{3}$$ hours
66.
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
(A) 1 : 2 : 4
(B) 2 : 1 : 4
(C) 4 : 2 : 1
(D) 2 : 4 : 1
Solution:
A : B = 1 : 2 B : C = 1 : 2 (Multiply by 2) B : C = 2 : 4 A : B : C = 1 : 2 : 4
67.
5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?
2 men and 3 women together or 4 men can complete a piece of work in 20 days. 3 men and 3 women will complete the same work in = ?
(A) 12 days
(B) 16 days
(C) 18 days
(D) 19 days
Solution:
According to the question, $$\eqalign{ & {\text{2m}} + {\text{3w}} = {\text{4m}} \cr & {\text{3w}} = {\text{4m}} - {\text{2m }} \cr & {\text{3w}} = {\text{2m}} \cr & {\text{3m}} + {\text{3w}} = {\text{3m}} + {\text{2m}} \cr & {\text{3m}} + {\text{3w}} = {\text{5m}} \cr} $$ 4 men can do work in 20 days 1 men can do work in 20 × 4 days 5 men can do work in $$\frac{{{\text{20}} \times {\text{4}}}}{5}$$ = 16 days $$\eqalign{ & {\bf{Alternate:}} \cr & \left( {2{\text{m}} + {\text{3w}}} \right) \times {\text{20}} = {\text{4m}} \times {\text{20}} \cr & \frac{{\text{m}}}{{\text{w}}} = \frac{3}{2} \cr & {\text{Total work }} \cr & {\text{ = }}\left( {{\text{2}} \times {\text{3}} + {\text{3}} \times {\text{2}}} \right) \times 20 \cr & = 240\,{\text{units}} \cr & {\text{5 men efficiency}} \cr & = 5 \times 3 \cr & = 15 \cr & {\text{Required number of days}} \cr & = \frac{{240}}{{15}} \cr & = 16{\text{ days}} \cr} $$
69.
Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?
(A) 14
(B) 17
(C) 12
(D) 15
Solution:
Vimal's 1 day work = $$\frac{1}{{20}}$$ Since, Vimal and Kamal can together complete in 12 days i.e. (Vimal + Kamal)'s 1 day work = $$\frac{1}{{12}}$$ Then, Kamal's 1 day work, $$ = \frac{1}{{12}} - \frac{1}{{20}} \Rightarrow \frac{2}{{60}} \Rightarrow \frac{1}{{30}}$$ If Kamal Works only for half a day daily, then his 1 day work becomes $$\frac{1}{2} \times \frac{1}{{30}}$$ = $$\frac{1}{{60}}$$ Therefore, 1 day work of both Vimal and Kamal, $$ = \frac{1}{{20}} + \frac{1}{{60}} \Rightarrow \frac{4}{{60}} \Rightarrow \frac{1}{{15}}$$ Hence, the work will be completed in 15 days.
70.
A can do a piece of work in 12 days. When he had worked for 3 days. B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work ?
(A) 6 days
(B) 12 days
(C) 4 days
(D) 8 days
Solution:
Total work = 12 Efficiency 1 units/day = 12 days time (A) After 3 days A finishes 3 units. ∴ Work left =12 - 3 = 9 units 9 units of work, 3 units/day = 3 days (A + B) (A + B)'s one day work = 3 units A's one day work = 1 unit B's one day work = 3 - 1 = 2 units ∴ B completes whole work in $$\eqalign{ & = \frac{{{\text{Total work}}}}{{{\text{Efficiency}}}} \cr & = \frac{{12}}{2} \cr & = {\text{6 days }} \cr} $$