Practice MCQ Questions and Answer on Time and Work

321.

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • (A) 5
  • (B) 6
  • (C) 7
  • (D) 8

322.

Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?

  • (A) 24
  • (B) 20
  • (C) 16
  • (D) 18

323.

Tapas works twice as fast as Mihir. If both of them together complete a work in 12 days, Tapas alone can complete it in ?

  • (A) 15 days
  • (B) 18 days
  • (C) 20 days
  • (D) 24 days

324.

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take $$\frac{8}{3}$$ more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

  • (A) 2 days
  • (B) 4 days
  • (C) 6 days
  • (D) 8 days

325.

There are three boats A, B and C, working together they carry 60 people in each trip. One day an early morning A carried 50 people in few trips alone. When it stopped carrying the passengers B and C started carrying the people together. It took a total of 10 trips to carry 300 people by A, B and C. It is known that each day on an average 300 people cross the river using only one of the 3 boats A, B and C. How many trips it would take to A to carry 150 passengers alone?

  • (A) 15
  • (B) 30
  • (C) 25
  • (D) 10

326.

Kiran, Vishal and Dinesh work in a juice factory. Kiran takes 2 hours to extract as much juice as Vishal can in 3 hours. Dinesh takes 5 hours to extract as much juice that Kiran extracts in 4 hours. A tank can be filled with juice in 48 hours, if all of them work together. How long will it take to fill the tank, if Dinesh alone is trying to fill the tank?

  • (A) 132 hrs
  • (B) 148 hrs
  • (C) 140 hrs
  • (D) 135 hrs

327.

20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?

  • (A) 12 days
  • (B) 14 days
  • (C) 13 days
  • (D) 15 days

328.

Two pipes A and B can fill a cistern in 12 min and 16 min respectively. Both the pipes are opened together for a certain time but due to some obstruction the flow of water was restricted to $$\frac{7}{8}$$ of full flow in pipe A and $$\frac{5}{6}$$ of full in pipe B. This obstruction is removed after some time and tank is now filled in 3 min from that moment. How long was it before the full flow.

  • (A) 8 min
  • (B) 3 min
  • (C) 5.6 min
  • (D) 4.5 min

329.

A can do a work in 36 days, B in 18 days and C in 12 days. Every 2nd day B and every 3rd day C, helps A .Then in how many days the work will be completed?

  • (A) 12
  • (B) 14
  • (C) 10
  • (D) 8

330.

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

  • (A) 40 days
  • (B) 50 days
  • (C) 54 days
  • (D) 60 days